01 / PROJECT ANALYTICS

Telecom rollout reporting across three regions

I consolidated work orders (OTs) for Región 5, Región 7, and Región 8 so the project manager could review approval status, requested hardware, installation readiness, and plan weeks in one report.

SQLPythonExcel / VBAOperational reporting
Reported workflow result3 hours to under 10 minutesTime to prepare the daily operational report.

My contribution: extraction, cleanup, status mapping, and a consolidated report for the PM. Decision it supports: which approved sites can proceed to installation and which need follow-up.

Technical approach · data model and reporting

One OT record represents each site. A separate equipment list preserves the one-to-many relationship between the OT and its radios, basebands, cabinets, licenses, and antennas. Statuses and plan weeks are standardized before aggregation.

The Excel export uses the same filtered OT records for its detail, regional totals, receipt-date breakdown, and validated installation plan. This keeps the summaries reconcilable with the source rows.

INTERACTIVE DEMO

PM rollout tracker

Synthetic sites and configurations · Illustrative workflow

Download the filtered OTs with date and status summaries, a validated installation plan, and source detail.

Work orders—
Validated OTs—
Installed sites—
Design/access blockers—
Progress by region
OT status and installations
Installation plan by week
Planned OTs vs. those installed
PlannedInstalled
Work order register
—
SiteRegionOT receivedOT statusPlan weekInstallation
SELECTED WORK ORDER
—